University of Cambridge researchers have developed a way to recycle used cement during steelmaking, giving demolition material a potential second use as the binder in new concrete. Announced on May 22, 2024, the process uses recovered cement in place of some of the mineral additions to a steel furnace. Cambridge reports electric-arc-furnace trials, while the accompanying Nature paper identifies a substantial cost before material reaches the furnace: heating old concrete to separate out its cement paste. For recyclers, that upstream step is central to whether the proposed process pays. [S1][S2]
The furnace does two jobs. Steel recyclers add minerals called flux to protect the molten steel and help remove impurities; the resulting slag floats on the metal. With the right composition, flux containing recovered cement paste can become clinker when the slag is cooled rapidly. Clinker is the mineral material that is ground and blended to make cement. In the experimental series described in Nature, the team produced 28 slags in induction furnaces over clean steel. Those experiments should not be confused with the electric-arc-furnace tests reported separately in Cambridge’s announcement. [S1][S2]
Getting the feedstock right requires more than crushing concrete. The paper says recovered cement paste was not commercially available at scale, although separation technologies existed. In the recovered sample tested, the authors inferred a mixture of 52% hydrated cement paste and 48% impurities, assuming the original cement matched their control material. Remaining aggregate raised the silica content; adding lime restored the chemical balance needed to make clinker. Contamination in steel scrap can introduce more silica and alumina, creating another demand for lime. The useful input is therefore a controlled mixture, not an interchangeable tonne of demolition dust. [S2]
In the researchers’ cost model, old concrete is heated electrically by 450 kelvin before crushing and sieving, with 85% heating efficiency. At an assumed recovered-paste purity of 75%, the calculation requires processing 5.25 tonnes of demolition concrete to deliver one tonne of recovered paste. These are model assumptions, not measured throughput or the purity of the sample described above. The paper identifies this heating stage as the dominant source of additional cost and power demand. [S2][S3]
Revenue from the separated sand also matters. Using UK cost assumptions for 2023, the supplement estimates £58.67 per tonne for a cement blend containing 50% recycled clinker when recovered sand sells for half the price of new sand. With no sand revenue, the estimate rises to £68.29. These are modeled costs, not selling prices: they exclude the finished cement’s profit margin, while the conventional cement benchmarks include one. The calculation counts changes to an existing recycling system rather than the full cost of building a new one. It also assumes transport of 320 kilometres to the steel furnace and another 320 kilometres to cement distribution, mostly by ship. A different supply chain would need its own calculation. [S3]
Who receives the emissions credit is still open to negotiation. The supplement credits the cement with all the benefit of avoiding conventional lime flux, which produces negative figures in parts of the calculation. That is an avoided-emissions credit, not carbon removed from the atmosphere. The authors say steel and cement producers would have to negotiate how to divide the benefit. Nor does clean electricity alone guarantee zero emissions: remaining conventional lime still carries emissions, and the paper describes dirtier steel scrap for which adding recovered paste would produce clinker without reducing lime consumption. [S2][S3]
Furnace capacity sets another boundary. A UK scenario in the paper suggests about 2.2 million tonnes of clinker a year, or roughly 4.5 million tonnes of cement when blended with calcined clay. That scenario assumes expanded electric-arc-furnace capacity, all UK scrap recycled domestically and a slag-to-steel ratio of about one to seven. It is not installed cement capacity. The authors also expect steel’s requirements to dominate chemical decisions because steel is the more valuable product. Cement output must fit that constraint, not merely the supply of old concrete. [S2]
The work is research from the team developing the process, not independent evidence of a commercial plant’s costs. Authors Cyrille Dunant and Julian Allwood disclose that they are named in its patent and are founder-directors of Cambridge Electric Cement, the company formed to promote its use. [S2]
Source documents
- University of Cambridge: Cement recycling method could help solve one of the world’s biggest climate challengeshttps://www.cam.ac.uk/stories/cement-recycling
- Dunant et al.: Electric recycling of Portland cement at scale (Nature)https://www.nature.com/articles/s41586-024-07338-8
- Dunant et al.: Electric recycling of Portland cement at scale — Supplementary Informationhttps://media.springernature.com/original/springer-static/esm/art%3A10.1038%2Fs41586-024-07338-8/MediaObjects/41586_2024_7338_MOESM1_ESM.pdf