NASA says Apollo 16 was moved from March 1972 to April 1972 because spacesuit, docking-ring, and battery tests were not finished in time. A Command Module fuel tank damaged during a launch-pad test then required the Saturn V to roll back to the Vehicle Assembly Building, where technicians replaced the tank and reassembled the stack. [S1]

According to NASA, three issues prompted the delay. Modifications to the spacesuits used by Commander John W. Young and Lunar Module Pilot Charles M. Duke were not ready. Testing of the Command Module docking ring jettison device was still needed after a Skylab-related test failure. Engineers also needed more data to reverify the Lunar Module battery capacity. [S1]

NASA says the mission was planned as a 12-day flight to the Descartes site in the Moon’s highlands. The prime crew included Young, Command Module Pilot Thomas K. Mattingly, and Duke; backups were Fred W. Haise, Stuart A. Roosa, and Edgar D. Mitchell. Crew training included simulators, lunar surface rehearsals, and geology briefings. [S1]

NASA explains that Mattingly, as Command Module Pilot, was to remain in orbit while Young and Duke explored the surface. His duties included visual and photographic observations, using instruments in the Service Module’s Scientific Instrument Module bay, and preparing for a deep-space spacewalk to retrieve film cassettes from that bay. [S1]

NASA says Duke developed double bacterial pneumonia after feeling ill during a December 1971 geology field trip in Hawaii. He was admitted to a hospital near Kennedy Space Center and recovered for a week while the other crew members continued training. The delay gave him additional time to resume his activities, although doctors did not expect his illness alone to affect the original launch date. [S1]

NASA says the rollback was triggered when workers accidentally over pressurized a fuel tank in the Command Module’s reaction control system during a test at Launch Pad 39A. The damaged tank could not be replaced at the pad, so the entire Saturn V was rolled back to the Vehicle Assembly Building, where workers removed the Launch Escape System tower and separated the spacecraft from the rocket. [S1]

In the Manned Spacecraft Operations Building, NASA says technicians separated the Command Module from the Service Module, removed its heat shield, and replaced the damaged fuel tank. Workers then reversed the process, restacked the spacecraft on the Saturn V, and returned the assembled vehicle to the pad in two weeks to support the new launch date. [S1]

Source documents

  1. 50 Years Ago: Apollo 16 Delayed One Month, Rolls Back From the Launch Padhttps://www.nasa.gov/history/50-years-ago-apollo-16-delayed-one-month-rolls-back-from-the-launch-pad/

Source: retained text from NASA. Other pages were not independently consulted.